Data Centre · Data Centre Cabling
10-rack colocation cage build with MPO trunks
Full cage build at a major UK colocation provider — cabinets, structured cabling, PDUs, and DCIM-ready as-built docs delivered in 5 weeks from PO.
- Completed
- Completed March 2026
- Duration
- 5 weeks
- Scale
- 10-rack cage · 12-fibre MPO trunks · CAT6A out-of-band
The challenge
Pinnacle Data Centres won a contract for a hyperscaler customer that required a 10-rack cage standing up in 6 weeks from PO — cabinets, structured cabling, intelligent PDUs, the lot. The customer's architect had a strict cabling spec (pre-terminated MPO trunks, no field-spliced fibre, length-matched copper leads) and wanted DCIM-ready documentation on day one.
The solution
We pre-built the cabinet stack in our workshop: vertical cable managers fitted, brush-plate floor entries cut, intelligent PDUs racked and tested. On site we craned the prebuilt cabinets in over a single weekend, ran the MPO trunks under the raised floor in armoured conduit, and finished the per-rack copper out-of-band cabling Monday–Wednesday. Fluke certifications, OTDR traces, and labelled photos went into the customer's DCIM the morning of handover.
Outcomes
- Cage delivered 1 week ahead of contract date
- Customer accepted DCIM documentation on first review — no rework
- Pre-terminated MPO eliminated splice variance — every link within 0.3 dB of spec
- Standard install template now reused across 4 subsequent cage builds for the same customer