Professional Services · Fibre Optic
Office relocation with fibre uplink continuity
New head-office fibre installed and tested before the move — Friday last desk in old office, Monday first desk in new office, no service interruption.
- Completed
- Completed November 2025
- Duration
- 3 weeks
- Scale
- 1 site · 60 desks · OS2 single-mode uplink
The challenge
Thompson & Associates' move from their old office to a new building 800 m away had to happen over a single weekend. Their phone system and case-management platform both lived on the existing fibre carrier handoff, and dropping either even briefly would have meant lost client work and missed court deadlines.
The solution
Two weeks before the move we installed and tested the new fibre uplink at the destination, including a parallel carrier handoff. On the Friday evening we cut over to the new fibre while staff were still working in the old office — the team carried laptops over Monday morning and connected to a network that was already up, tested, and identical to what they'd left behind.
Outcomes
- Zero downtime during the relocation weekend
- Phone numbers + case-management URLs unchanged for clients
- Old fibre kept live for 30 days as fallback — never needed
- Project completed within the agreed 3-week window